2021-08-24 Meeting Minutes - General
Goals
Discuss/review Fall Rover Design 2021 Timeline
By end of Fall, all design will be done (both drafts, one PDR, one CDR)
See timeline for more information
Each project/subteam has their own section on the timeline (e.g: gimbal, drivetrain, arm...)
Update & Action Items
Member | Update | Action Items |
|---|---|---|
@Ethan Cronier (Deactivated) |
|
|
@Former user (Deleted) |
|
|
@Austin Tailon Huang (Deactivated) |
| |
@Olabisi Sanusi |
| |
Ali |
|
New Tasks
BLDC motor test rig
New mechanical training needs to be tested
Build code for arm prototype; hopefully by the end of next month, assigned Ali/Medina
Find someone to lead each mechanical project (science, ebox)
Science mechanism - ??
E-box mechanism - Olabisi
Need to check if the team codes for SOLIDWORKS work; they probably don't right now. As of right now, the MME codes are being used, but that cannot continue as non-MME students may need access as well
Need more storage bins in bay/better fastener organization;
Not enough places to put fasteners
General Notes
@Former user (Deleted) is stepping down as drivetrain lead, @Emily Adam (Deactivated) will be taking over
For drivetrain prototype, code needs to be fleshed out soon, will happen w @Emily Adam (Deactivated) and @Former user (Deleted)
Wiring will happen on site, testing will be done in Oakville
New training has been finished. Needs to be tested
Team is taking a small break; will come back to design sprints on September 1st