2021-01-26 Meeting Minutes - General

Goals

  • Revamping the Drivetrain
  • Switch the arm motors to harmonic drive gearboxes
  • Fix the 2021 Rover assemblies

  • Force-sensitive claws


Update & Action Items

MemberUpdateAction Items

Asha ME, Emily A, Rehnuma T

  • Gathered all 3D prints and prepared all test tubes for assembly
  • Camera mount design done (needs to be reviewed)


Jasmine M, Rehnuma T
  • Still missing some fasteners
  • Preliminary design review 2021-01-24
    • Minor Mech Changes
    • Add connectors to CAD
    • CAD updates!
  • Need to sort and catalog the fasteners
  • Final design review afternoon of 2021-01-30
  • Order parts by 2021-02-01


Mathieu H, Austin
  • Probably passing this off somewhat soon
  • Printing out test rig for Younes
  • Please send me your machining files, we will be placing an order with Wyrks tmrw
Ethan C, Rehnuma T
  • Rev 1 complete
  • Protective shell pending
  • Need to create BOM and start ordering
  • Blocked by Ayesha (BMS)


Abdul H
  • Got all the parts, except the fasteners


New Tasks


Task

Name

SAR Video

Austin, Jasmine (after main e-box design done)

Force-sensing claws

Shreshth Mehra

Drivetrain revamp

Medina Colabrese

Max Apitz-Grossman

Emily Adam

Andrew Tersigni

Fixing 2021 CAD

Alaina (?)

Ethan Cronier

Harmonic drive

Emily Adam

Battery

Ethan, Rehnuma, austin

New mechanism design




General Notes

SAR update

https://docs.google.com/document/d/1nHkIZ7RM1YnBL17pz-qTBCnfkuRY-as1CBwRSMsuBVc/edit?usp=sharing