Current State of Progress & Action Items
Prototype
- Mechanical assembly
- Changes successfully made to make more robust
- Upgraded bearing plates to have more mounting holes, added loctite to gearbox mounting screws, replaced wood screws with 1 1/4" long screws around the motor
- Added horizontal support beams to stiffen pegboard
- Deflated the tires slightly so that we could bring the hubs closer together, adding more clearance between the wheel and the frame
- Mounted controls board
- To do still:
- Bring Wheelez to an equal pressure → borrow Medina's bike pump!
- Assemble the legs back on the chassis
- Print battery and weight holders, add to bottom layer of chassis
- Cut and add wheel treads
- Create & fabricate attachments to keep differential bar in place
- Changes successfully made to make more robust
- Learnings so far:
- Flexing in EVERY joint
- Should minimize wiggle by having press-fit bearings/bushings secured with Loctite or glue
- Research other rover designs or other methods in general for stiff – but still flexible – rocker-bogies
- Weight of motors in the current position is also causing some bending of the legs
- Definitely use metal spacers or more robust plastic spacers for the final drivetrain
- Flexing in EVERY joint
- Learnings so far:
- Wiring/Controls
- All but sensor connections are completed
- To do still:
- Update motor assignment in code
- Plug in motors
- Wire up the current sensors to the ADC and Raspberry Pi
- Debug current collection
- Click to add a new task...
Update & Action Items
Member | Update | Action Items |
---|---|---|
Emily Adam (Differential bar) |
|
|
Former user (Deleted) (Wheel connections) |
|
|
Former user (Deleted) (Chassis) |
|
|
Former user (Deleted) (Frame/structure) |
|
|