2021-09-16 Meeting Minutes - Drivetrain
10 Days until Prototyping Conclusion!
→ Wrap-up meeting, next Sunday 7pm ET (Sept. 26th)?
Goals
Review prototyping progress
Introduce new member?
Discuss & assign bonding prototyping
Discuss budget plan for Drivetrain
Current State of Progress & Action Items
Prototype
Mechanical assembly
Changes successfully made to make more robust
Upgraded bearing plates to have more mounting holes, added loctite to gearbox mounting screws, replaced wood screws with 1 1/4" long screws around the motor
Added horizontal support beams to stiffen pegboard
Deflated the tires slightly so that we could bring the hubs closer together, adding more clearance between the wheel and the frame
Mounted controls board
To do still:
Bring Wheelez to an equal pressure → borrow Medina's bike pump!Assemble the legs back on the chassisPrint battery and weight holders, add to bottom layer of chassisCut and add wheel treadsCreate & fabricate attachments to keep differential bar in place
Update & Action Items
Member | Update | Action Items |
|---|---|---|
@Emily Adam (Deactivated) (Differential bar) |
|
|
@Former user (Deleted) (Wheel connections) |
|
|
@Former user (Deleted) (Chassis) |
|
|
@Former user (Deleted) (Frame/structure) |
|
|