May 30, 2022 - Sync Up

Attendants

  • Austin

  • Peter

  • Logan

  • Ari

  • Anna

  • Max

Agenda

  • Sync up after 2 week block


ODrives

  • Odrives are still currently not functional - motors are not spinning and there are connectivity issues and @Jahnavi Thota is working on it with top prioritiy

  • Will buy a BLDC motor controller to test with in the mean time while we are working on getting the odrives running

Software

  • CAN integration plan onto drivetrain still in progress - @Orson Marmon working on making a timeline with milestones and design doc, Colin to integrate in person

 

Business

  • EngSoc coming up on Jun 6, 2022 , get requests in by Jun 3, 2022

    • Last term asked for ~1200, should ask for a similar amount this term

    • Focus on requesting safety related items

    • From last round need to purchase the thermal camera and helping hand (potentially soldering tips)

    • Arbor press and hot plate are current ideas, will discuss more in leads

  • Working on website in progress

    • New pictures are a priority for team and leads

EE

  • PDB, BMS and Buck are being reworked

  • Chelsie and Jason are working on BLDC

  • Science board has been assembled / SPI host boards have been tested

ME

  • A1 is almost done - epoxy failure just needs to be redone

  • A2 is completed

  • A3 and A4 still in progress

  • Parts on science need to be hashed out - figure out what is going on for Air Manifold

 

PM - Continuation

Project Management - Introduction

  • Showcase and goal setting needs to be prioritized first

  • Weekly / monthly / term wide goal setting to be discussed by Jun 2, 2022