SAR 2024 Electrical Tasks
Drive Train Tasks
Task | Time Required | Resources |
---|---|---|
Test the PDB | 1 week | 1 person |
Get the 17V buck working | 2 months (board spin) | 1-2 people
|
Plan out the harnessing for the drive train | 1 week | 1 person |
Assembly harnessing for the drive train | 2 weeks | 1 person |
Arm Tasks
Task | Time Required | Resources |
---|---|---|
Get the 24V buck working | 2 months (board spin) | 1-2 people
|
Plan out 24V power distributions | 2 months (board spin) | 1-2 people
|
Plan out harnessing for the arm | 1 week | 1 person |
Assembly harnessing for the arm | 1 week | 1 person |
Contigent Tasks
Task | Time Required | Resources |
---|---|---|
Spin the PDB (assuming and issue arrises) | 1 month | 1-2 people
|
Boot strap the power system (if shit doesn’t work out) | 1 week | 1 person |