Timeline

Schematic Reviews:

Power Schematic:

REVIEW THE DIODE CIRCUIT

Schematic Review - Assigned to @Rayyan Mahmood (Completion date: September 8, 2024)

GNSS Schematic:

Schematic Review - Assigned to @Rayyan Mahmood (Completion date: September 8, 2024)

MCU Schematic:

Schematic Design - Assigned to @Hoang Dang (Completion date: September 11, 2024)
  • Main components/areas to work on: Crystal oscillator, Debug connections, nRESET

    • Components such as LEDs, TPs, Pull up/down resistors can be added after first schematic review

    • Consult Billy on Test button, and other firmware geared requirements

    • When STM schematic completed, contact Billy to assign MCU schematic review

  • IMU & Level Shifter schematics will be reviewd after MCU

CAN Transiever:

Schematic Design - Assigned to @Rayyan Mahmood (Completion date: Sunday, September 15, 2024)
Schematic Review - Assigned to @Hoang Dang (Completion date: September 18, 2024)

External Antenna:

Not certain yet if to be implemented - though implementation is much more simple than anticipated

If implemented:

  • Will be added by @Rayyan Mahmood

    • Will include jumper to switch between external and internal

    • Will have empty pads to implement pi network if needed

    • Will be added into schematics by September 29

Layout Timelines:

(Will be worked on once all schematic reviews have been completed) - September 14, 2024

@Hoang Dang && @Rayyan Mahmood need to determine time

Tentative layout completion date: October 15