Tasks (Links to full description) | Brief | Due Dates | Task Owner | Risk Management | Timeline | PDR Component |
---|---|---|---|---|---|---|
Redesign of gimbal design and stable mount to the rear of the rover | Dec 23, 2024 | @Vedha Mereddy | MajorSUSTAINING | ON track |
PDR Completed? | |
Antenna mounting and possibly single axis motorized antenna design | Dec 23, 2024 | @Senna Barborini | CriticalSUSTAINING | On Track |
PDR Completed? | |
Sensor skeleton | A skeleton diagram for all robot sensors following software requirements | Oct 12, 2024 | @Saheed Quadri | Critical SUSTAINING Blocking | Delayed |
PDR Completed? |
Wheels need to be redesigned to be larger, have better traction, retain deformability and most importantly feature spokes that smoother enable turning on the spot | Nov 15, 2024 |
| Major SUSTAINING | Unassigned |
PDR Completed? | |
GPS Mounting and Integration | Collect software requirements and mechanical considerations for permanently mounting the GPS and integrating with the rover electrical system | Jan 30, 2025 | @Joseph Schuurman | critical | AT RISK |
PDR Completed? |
Rev 1 Autonomy Depth Camera D435 Mount | First iteration of camera mounts suitable for software testing | Jan 30, 2025 | @Adam Selalmatzidis | Major | AT RISK |
PDR Completed? |
Wheel Jig Design | Design a setup to quantitatively and qualitatively test wheel design options | Jan 31, 2025 | @Tasi Dzikiti | Major Sustaining | At Risk |
|
Base station and operator controls station | Build the comms station, define driver and operator interface, define and build any desire customizations | Feb 14, 2025 |
| Major | Unassigned |
|
Arm Camera Mount design | Complete the design for mounting a teledyne flir camera on axis 5/6 gearbox | Feb 5, 2025 |
| Minor sustaining | Unassigned |
|
Modular Arm / Science module mount | Quick release system for mounting the arm and science subsystems to the front of the rover | Jan 31, 2025 |
| critical | Unassigned |
|
Arm Encoder mount design | Modify the current encoder mounting parts for each axis to a new revision for the ERCK SPI encoders | Jan 24, 2025 | @Shahzeb Ali . | Minor | On Track |
|
Science system planning | Design science system architecture and define our approach to achieving competition requirements | Jan 31, 2025 |
| Critical CriticalBLocking | Unassigned |
|
Note: Tasks are currently high level and can be further split up