MACHINING & ASSEMBLY-READY SUB-SYSTEMS DUE JAN 4TH!!!

Goals

  • Review the state of each sub-system and what's left to do
    • Delegate if necessary
  • Review member availability next term

Required Items

  1. Final CAD → parts are ready to be machined, tolerances are in, fasteners are in, does not break the main assembly
    • Please upload to GrabCAD (sad)
  2. BOM!!!
  3. Part drawings 
    • Priority is Demtool drawings. Send for review as soon as they're done
    • Make a drawing for every part we're getting machined. Carbon fibre tubes can be put into the same drawing file, different sheets
  4. Assembly drawing
    • The goal is to make this detailed enough that someone not familiar with your sub-system can assemble it without you there

Update & Action Items

MemberUpdateAction Items
Former user (Deleted) (Chassis)

Former user (Deleted) (Wheel connections)

Emily Adam (Differential bar)
  • Finish up my drawings
  • Order all of our parts!
  • Send parts to sponsors!!
  • Finish bond testing!!! (Jan 4th)
  • Prepare tread plan
Former user (Deleted) (Frame/structure)

Former user (Deleted)

Elizabeth Jung (Bonding fixture)
  • Send Emily hand drawn ideas until approved → create CAD → get reviewed → iterate & create BOM


New Tasks

General Notes