MACHINING & ASSEMBLY-READY SUB-SYSTEMS DUE JAN 4TH!!!
Goals
- Review the state of each sub-system and what's left to do
- Review member availability next term
Required Items
- Final CAD → parts are ready to be machined, tolerances are in, fasteners are in, does not break the main assembly
- Please upload to GrabCAD
- BOM!!!
- Part drawings
- Priority is Demtool drawings. Send for review as soon as they're done
- Make a drawing for every part we're getting machined. Carbon fibre tubes can be put into the same drawing file, different sheets
- Assembly drawing
- The goal is to make this detailed enough that someone not familiar with your sub-system can assemble it without you there
Update & Action Items
New Tasks
General Notes