Goals
- Switch the arm motors to harmonic drive gearboxes
- Fix the 2021 Rover assemblies
- Force-sensitive claws
Update & Action Items
Member | Update | Action Items |
---|
Alaina Hansen | - Handed off science mechanism
- Picked up Spaenaur order
| - Will be handing off gimbal this week
|
Asha Mills Emmett | - Picked up parts for science
| - Sort through Spaenaur fasteners
|
Ethan Cronier | | - Figure out where to put new battery - 2022
- Assembly stuff - Tasks for someone in person
- Assemble new rover comms bracket when fasteners and brackets come in
- Send message to Abdul about base station assembly
|
Rehnuma Tasneem |
| - Pick up science camera
- Work on assembly with Jasmine
- New science camera mount design
|
Max Apitz-Grossman | - Ebox baseplate and box tubing connectors (done before break)
| - Need to choose quick-release pins from McMaster Carr
|
Medina Colabrese | - Still working on wire management
| - Finish collecting data
- Determine wire lengths, required harness sizes, etc
|
Abdul Haseeb |
| - imma do what Asha tell me
- Base Station assembly - parts in the bay
|
Austin Huang | - Cleaned up main assembly CAD
| - SAR Planning - Plan discussion topics for each video segment, reach out to different subteams for info
- Continue to update and investigate CAD
- Make machining instructions/drawings for encoder stuff (will be done ASAP!)
|
Jasmine Milan | | - Figure out what is going on with material!!=
- Touch base with electrical team on size of cords going through ethernet connector hole to update strain relief solution
- Once strain relief approved, update CAD (Message Lead)
- Talk to Ethan about location of batter/estop connector hole
- Dimension and placement of Electrical Components (In talks with Electrical)
- Machine shop & COVID training
|
Emily Adam | - Made a revised version of the funnel pieces for Science
- Picked up the Science mechanism from Alaina
| - Finish Science assembly with Asha...
|
Andrew Zhang |
| - Finish arm model
- Collect rotational inertia data
|
New Tasks
- Work on revamping the drivetrain!
- Look into updating current arm motors to harmonic drive gearboxes
- Fix the 2021 rover assemblies
- Work on force-sensitive claw
General Notes
Overview
- SAR Update
- State of emergency in Ontario
- Assembly done locally
- New projects to work on!
SAR update
- This week and next week we will focus on assembly of subsystems
- I am currently arranging with Graeme Adair, our main contact to go into the bay, to go in and organize the parts to build the subsystems into separate boxes which can be picked up by the members building the systems
- If you require any extra tools to build, let me know, there is talk of members buying the tools and getting reimbursed
- The video planning is going well, have a look at the document and make comments and recommendations.
https://docs.google.com/document/d/1nHkIZ7RM1YnBL17pz-qTBCnfkuRY-as1CBwRSMsuBVc/edit?usp=sharing
Rover Assembly
- Arm : Mathieu
- Science : Asha and Emily
- Gimbal and e-box: Jasmine and Rehnuma
- Base Station : Abdul
State of Emergency in Ontario
- Stay-at-home orders effective Thursday
- Trips outside your house are limited to essential trips only
- Not sure yet what that means for us
- I will investigate and keep you all in the loop