Attendants
Ethan
Austin
Cindy
Clare
Farris
Grace
Max
OrsonAnnaEmily
No software updates
We are not going to make SAR
Sponsorships
Everyone is responsible for attempting to acquire sponsorship
ask your old employer for financial sponsorship
Sponsor package is in Confluence
Working on getting people reimbursed
Mechanical
part tracker - use this
Boms
need bom tracker - COTS
what stuff are we ordering?
misumi parts?
mcmaster-carr parts?
carbon fiber tubes?
servo city parts?
Stock
order all the stock
you cannot machine without stock
once stock is ordered, anyone can sign up to make a part
Design
why are we still designing major components
Electrical
boards status? - trackers
wiring status?
wiring diagram status?
do we have a charger for the battery
does science still need to be discussed?
Firmware
bldc motor testing - encoder post reduction issues sorted?
Science
Science report?
What chemical tests are being used
might be mis-understanding with the CO2 sensor
Business
Eng Soc funding from F2021 was released! There is also still funding left over from past terms from Eng Soc, Mech/Electrical leads can check the Master Tracking Sheet to see what we have left! Those things can all be ordered as soon as you’d like. Reminder that Eng Soc funding can only be used for what item we requested it for!
EXPIRING FUNDING: Mechanical, you have $535 to spend on a drill and or angle grinder. This must be purchased and processed by the end of the term. If we don’t use it, the money is gone forever.
I have no further updates for WEEF, other then we are working around them and going straight through Peter to Finance. Cindy, I will start collecting your documents and going through them again so that if it works with our other purchases to go through Peter, we can do yours right away.
Thanks to Emily for submitting lots of purchases and catching some “odd” scenarios for the tracking system! I will update it this week sometime. If the following comes up, please talk to me:
Eng Soc Reimbursement (All the same steps will apply, it’s just a different reimbursement form!)
Paying with your WAT card
Submitting something that we got for free but needs to be counted as part of the Rover Budget
Overall, new tracking system is working great! :))
Software
-
STAR GOALS
specific, testable, attainable, and relevant
Mechanical
create COTS tracker
fabricate 0116
fix the printer
order SKF bearings
order Misumi parts
another part to fab?
order more stock - at LEAST stock for 5 part types
Electrical
finish science board
make a tracker
Firmware
200, 202 - stock already ordered - max
Electrical
battery charger - figure out if we are borrowing or buying - then buy this week
make a tracker - schematic, board/layout completion, parts, assembly
nail down timeline/deadline for wiring diagram
Firmware
try to figure out the bldc - post reduction or hall effect sensor
if issue sync up with team on this issue
Science
1-2 weeks figure out chemical tests and document
move science report to google drive, link in confluence
Lead
send reimbursement forms to Peter
General notes
prioritize drivetrain
RLS - Caleb
Meeting for Science mechanism - everyone
slides - just explaining how it works
lack of understanding of how the mechanism works
Ethan Cronier setup the meeting
Arm meeting - everyone
Austin Tailon Huang (Deactivated) setup meeting
no gimbal
lack of communication problems
documentation of wiring diagram
maxon motors coming soon
Fictiv - email chain send to austin
https://drive.google.com/drive/u/1/folders/10DCpUaU5t6Dnjd6-QMzRBkAHRZuIbw6s - google drive for team
check up with old non-csa battery charger
What are we doing after SAR?
guage progress after 2 weeks, see how it goes - go from there.