Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Step-by-step guide

...

    1. Update the Percent complete to reflect current progress.
    2. Update the Health (Red, Yellow, Green).
    3. Add a comment detailing any key items for the status update (activities or deliverables completed, issues arising, changes to the schedule, etc.

...

Info
iconfalse
titleNeed Help?

Contact the IST Service Desk at helpdesk@uwaterloo.ca or 519-888-4567 ext. 44357.