2/15/2023

2/15/2023

Weekly Updates

Member

Main Project

Status

Update

Action Items

Member

Main Project

Status

Update

Action Items

Ari Wasch (Deactivated)

BMS

⛔

 

 

David Choi

DD Current Sense / Comms

✅🚹

Any update on the DD Current Sense part selection? Any update on Comms?

  • Set up comms for software--untested

  • Making RS422 wires for firmware

  • Ordered new boards for RS422

  • Making wires

  • Focusing on firmware until SAR

Farris Matar (Deactivated)

PDB/OTS BMS

✅🚹

  • Ordered charger – recieved

    • got everything to wire itup

    • making cables

    • main power cables done

 

  • Setup battery to charger connections

  • getting charge/bms to work

Logan Hartford (Deactivated)

Lead

✅

  • Finished setting up Altium team licenses

  • Signed up for Altiums training curriculum

  • Made guide for getting power rails up

  • Discussed new onboarding stream with peter:

    • 1. training

    • 2. testing and integration workshop

    • 3. getting started with altium

    • 4. cookie cutter, full term board design project

      • Make project collaborative

        • altium 365

      • compare work at regular deadlines, review each other, then reviewed by senior

      • Work session should be grunt work--is the collaborative period

    • 5. Resume and application workshops

      • Farris’s cohort has an interview question bank

    • 6. novel PCB design projects

    • 7. keeping people engaged with the team

  • Review the new DD current sense schematic if avaialble

  • 5V layout review

  • Create a presentation for testing and integration workshop

  • brainstorm some good cookie cutter board projects

    • code with me style or just list tasks and provide necessary instructions

    • One small part is code w me then move to something more advanced and apply the principle

    • Reading datasheets

    • Calculations

    • Mention the fundamental of the electrical concepts-why math works

    • keep within the scope of board design

    • Have a repository of concept explanations

  • Reading week next week

  • Make a better wiring diagram with Draw.io

  • Ideas:

    • communication protocol--use osciliscope

    • I2C multiplexer

    • roulette board-555 timer--LED roulette board

    • DD current sense board but simpler

    • simple sensor board

  • Set up meeting with Rishith

  • Report

  • drivetrain by sunday

  • electrical support needed

Muhammad Tanveer

Comms

✅🚹

Any update on Comms?

 

Rayaan

5V OTS Buck

✅

Any update on the power replacements?

  • Met with Billy about the DD current sense board

  • Set up a meeting for the weekend

  •  

  • Set a meeting meeting for reimbursment

  • Meet with billy

Rishith Bomman (Deactivated)

PDB

✅🚹

Any updates on PDB Rev 4.1?

  • Went through comments in layout revie

  • add new load monitoring sw’s

Wolfgang Windholtz (Deactivated)

Science / Support

✅

 

 

Yuchen Lin

DD Current Sense / Comms

✅

Any update on the DD Current Sense part selection? Any update on Comms?

  • Had a meeting with Rayaan

  • This Saturday will be designing the board together

  • Would like to participate in the onboarding board

Priority I Tasks:

Task

Discussion Questions

Answers

Assigned To

Task

Discussion Questions

Answers

Assigned To

Get the bare minimum electrical systems working for the drive train to be able to move
  • What is the bare minimum electrical system?

  • What are all the all the ways we can achieve this?

  • New requirements--Need to power:

    • Jetson - 17V, 10W-30W

    • Gimbal

      • Search up nominal voltage and current draw for gimbal motor

      • Zed2: 380mA @5V

    • Vector Nav - 5V, 250 mA

    • Anenna - 24V 1.5A

    • Pi - 5V 3A

    • What are the power requirements for each of these?

  • Encoders need 5V, mostly a current ref

    • 20mA per encoder

    • 48-5V buck

  • 48V to each motor

  • Apparently the Odrive supplies 5V to the encoders so no need for a buck

Total SAR Power Requirments

17V - 4A
5V - 380 + 250 + 3A => 4A
24V - 1.5A

Rayaan

Validate the OTS BMS
  • How can this be done?

  • How easy of a project is this?

  • 3/5 tough

  • Use resistors divider board to validate basic functions

    • For checking over-voltage?

    • Hook up the cells to the BMS and test basic functions

  • Someone has definitely done battery emulation before

    • google it

Farris Matar (Deactivated) (starting next week)

Create a SOP document for how to charge the LiPo battery pack
  • With vs without the BMS

  • What is the safest way?

  • What is the most convenient way?

  • Any concerns?

  • Should always charge it using a battery charger

  • Have the BMS hooked up as well

  • Connector solution

  • Put safety warnings, storage instructions etc

Yuchen Lin

Complete Rev 4.1 of PDB
  • Do we have time for a work session this weekend?

  • Yes

Rishith

Validate the electrical functionality of the LED matrix
  • What exactly does this consist of?

  • What needs to be done to verify?

  • Send a digital signal to the neopixels, bitshifts

  • Just need to hit it with PWM to set the colour of the whole thing

    • arduino town

David Choi / Rishith

/ Farris Matar (Deactivated)

Set up 2.4 Ghz bands

 

  • working on instability issue

    • Should be fine with one antena

David Choi

Priority II/III Tasks:

Task

Priority

Status

Comments

Task

Priority

Status

Comments

Wire up the ARM

II

Waiting on mechanical/firmware

 

Wire the drivetrain

II

Waiting on mechanical/firmware

 

Set up 5 Ghz bands

III

Working on priority I comms first

 

Set up 900 Mhz bands

II

Working on priority I comms first

 

Active Projects:

Project

Currently Assigned To

Ticket

Due Date

Comments

Priority Level

Project

Currently Assigned To

Ticket

Due Date

Comments

Priority Level

PDB

Rishith Bomman (Deactivated) /

Farris Matar (Deactivated) / Rayaan

PDB Rev4 - Design and Assemble the PDB

Dec 19, 2022

  • Performance testing complete

  • Some small schematic and footprint issues across the board

  • 17V performed well except on start up

  • 5V is very noisey

HIGH

BMS

Joshua Harper / Ari Wasch (Deactivated) / Olivia

BMS - Design and Assemble the BMS

Apr 19, 2023

  • One BMS has been assembled

  • Basic non-performacne and non-firmware tests have been done

  • An off the shelf replacement is being sourced

HIGH

Comms

Yuchen Lin / Logan Hartford (Deactivated)

Comms

Oct 31, 2022

 

HIGH

Science

 

Science - Assemble & Test

Apr 19, 2023

  • Need one or two people to own the assembly and testing of the science boards and work with Ivan Lim (Deactivated) and Wolfgang Windholtz (Deactivated) to ensure the board is ready for competition.

  • Found two assembled boards but none of the parts if Ivan Lim (Deactivated) / Wolfgang Windholtz (Deactivated) have any ideas please let me know. Otherwise we’ll just order more parts.

  • Ivan Lim (Deactivated) / Wolfgang Windholtz (Deactivated) Both of the assembled boards are missing a lot of parts, do the boards have a bunch of population options?

MEDIUM

SPI LVDS

Farris Matar (Deactivated)

SPI LVDS - Assemble and Test

Apr 19, 2023

  • SPI LVDS Host boards should have been assembled

  • SPI LVDS Peripheral parts and boards should be in the bay now, pending assembly

  • Harnesses need to be ordered in order to wire them up together and do testing

MEDIUM

RS422

David Choi / Farris Matar (Deactivated)

RS422 - Assemble and Test

Apr 19, 2023

  • Farris Matar (Deactivated) verified the design and was able to send data using the boards

  • 3 Boards have been assembled and tested

MEDIUM

LED Matrix

 

LED Matrix 2022/23

Apr 19, 2023

  • LED matrix has been located

  • Should work, just needs power and a PWM signal

MEDIUM

Digital Display Current Sense Board

Olivia Markham / David Choi / Yuchen Lin

Current Sense Display

Apr 19, 2023

  • Currently in the schematic design phase of the project

LOW