Member

Main Project

Update

Action Items

Ari Wasch

BMS

  • Review the buck schematic and calculations

  • Support in-person firmware work meeting

  • Test new 48V battery

Chealsie Bains (Deactivated)

BLDC

Solar

Any update on BLDC layout?

Ethan Romero

PDB

Any updates on getting started with PDB?

  • Review the buck schematic and calculations

Farris Matar

PDB/BMS

  • Worked with Rishith Bomman on buck converter calculations & part selection

  • Reviewed 24V Multiphase buck schematic

  • Continue working with Rishith Bomman on PDB schematic - plan is to have schematic done by next Wed.

  • Look for replacement 48V power supply

Ivan Lim

Science

Any updates on powered tests for science?

Jason Gao

RS422

BLDC motor controller

Joshua Harper

BMS

  • Review the buck schematic and calculations

  • Continue working on BMS schematic

Logan Hartford

Multiphase Buck Converter

  • Review the buck schematic and calculations

  • Support Paul Kokhanov in layout

  • Create a parts creation tutorial specific to our library

  • Support in-person firmware work meeting

    • 10am Sunday

Paul Kokhanov

Multiphase Buck Converter

  • Met with Logan Hartford , got schematic up for review

  • Review received from Farris

  • Working on Layout

  • Consulting Review comments from Farris

Rishith Bomman

PDB

Met with Farris Matar to go over calculations. Picking components

  • Finish Picking Components and start on schematic

Taylor Mcnabb

SPI LVDS

Wolfgang Windholtz (Deactivated)

Science

...

  •  Send Farris your Altium email if you want a team license
  •  Test science
  •  Test RS422 board (Reach out to Jason for more information)
  •  Finish/test SPI LVDS board
  •  We are working on wire harness this weekend
  •  Support firmware & software
    •  10

Deadlines:

  • Have all PCBs designed by the end of July

    • Buck, PDB, BMS

    • Have boards ready for design review and layout in two weeks

  • Have boards and parts in hand by the end of August