Update

Action Items

Aidan Gratton

 

Ari Wasch

  • Submitted BMS for review

  • Co-op stuff

Finish BMS layout

Chealsie Bains (Deactivated)

  • Update on Jetson carrier & parts?Resolved all the remaining errors with the Jetson carrier

  • Finished UART debug layout, buck converter placement reviewed by Cindy Li (Deactivated)

  • Route buck converters

  • Route high speed & ethernet parts of Jetson

Cindy Li (Deactivated)

 

Farris Matar

  • Learn PDN this week with Chealsie Bains (Deactivated), Logan Hartford, and Taylor Mcnabb

  • Work with Lance to review layer stackup & copper thickness & dielectric separators on PDB

  • Look into upgrading Discord bot - may be a way to send a custom JSON so the bot messages are cleaner or provide better info

  • Work with Taylor Mcnabb to complete SPI LVDS Master layout

  • Review Ari Wasch's BMS layoutCoordinate BLDC controller discussion for next week’s meeting or some alternate time

  • Purchase hot air reflow station & battery charger

Lance Bantoto (Deactivated)

Ivan Lim

  • Select GPIO expander for science

Jason Gao

  • Update on SPI LVDS breakout boards? SPI Slave Board schematic almost complete

  • Bay cleanup last weekend

  • RS422 Breakout layout revised based on layout review

  • Motor controller requirements

  • SPI Slave Board

  • Order RS422 components

Logan Hartford

  • Just got my altium license back

  • Should be able to make some progress by next meeting.

Taylor Mcnabb

  • Continue working on SPI LVDS Master layout

Wolfgang Windholtz (Deactivated)

  • Made a general plan

  • Need to Find GPIO expander I2C

New Design Process Stage: Scope & Requirements

What to do for scope:

  • Figure out the main purpose(s) of the board

  • Major criteria, requirements, any parameters

  • Who is involved in the board, keeping up with those involved to adjust for any changes