Weekly Progress Update

  • DD current sensing board

    • Status:

      Status
      colourYellow
      titleIn Progress

    • K:\University of Waterloo Robotics Team\Mars Rover\Sandbox\Senna Barborini\Torque Jig

    • N/A

    • Component selection is nearly complete, still needing the IC. After the components have been selected, schematics and layout can be made on Altium. Altium has been installed.

  • Bearing Installation on DT

    • Status:

      Status
      colourGreen
      titleCompleted

    • N/A

    • N/A

    • All six wheels now have a smother drive as the bearings ensure constant concentricity. There is significantly less friction opposed to the prior configuration where the Odrive casing would rub against the aluminum mount.

  • Communication Gimble

    • Status:

      Status
      colourYellow
      titleIn Progress

    • K:\University of Waterloo Robotics Team\Mars Rover\Sandbox\Senna Barborini\Wave Nano

    • image-20240920-150425.png

    • Assembly is nearly complete. What remains is modeling how the servo actuates the gimbal. Then, physical production of the prototype may begin.

Tip

Meeting Minutes with Supervisor

<insert the meeting minutes links>

Info

Next Week Plan

  • Communication Gimbal

    • Status:

      Status
      colourYellow
      titleR&DDevlopment

    • N/A

  • Electrical project: DD current sensing board

    • understanding the math and theory behind it

    • Complete component selection (voltage sensing, current sensing IC, STM chip, CAN transciever)

    • Complete the schematic and conduct a design review

    • Complete the Layout

    • Generate the Gerber and be ready to send to manufacture