Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Member

Main Project

Update

Action Items

Ari Wasch

BMS

  • Update on PDB + BMS firmware?

Chealsie Bains (Deactivated)

Jetson Carrier

  • Update on layout for Jetson Carrier?

Farris Matar

PDB/BMS

  • PDB + BMS and RS422 completed fab, shipped out yesterday

  • PDB test plan & test plan template created

  • Wiring diagram for drivetrain + e-box completed

  • Start wiring diagram for arm, gimbal

  • Documentation for PDB + BMS board

  • Keep up with PDB + BMS and RS422 shipment

Ivan Lim

Science

  • Update on science layout?Finished First Revision of Placement of Science Board

  • Begin With Layout

  • Implement changes from reviews

Jason Gao

RS422

BLDC motor controller

  • Reviewed Jetson CAN/UARTdebug board placement

  • BLDC Layout still in progress - changes from schematic review

  • SPI peripheral schematic almost complete, finalizing connector selections to the 2 encoders

  • RS422 Testplan + assembly + testing

  • BLDC layout

  • SPI peripheral schematic

Logan Hartford

Multiphase buck converter

  • Ordered the buck board

    • Reviewed the Jetson buck converter layouts

  • Probably not too much, midterm szn

Taylor Mcnabb

SPI LVDS

  • No update on SPI LVDS, busy with co-op & midterms

  • Co-op hunt is over, will resume work on board post-midterms

Wolfgang Windholtz (Deactivated)

Science

  • Update on science layout?

...