Topic 4: Sub-team Updates - Mechanical
- Bug Ethan about science
Push deadlines closer? (burnout risk)- Science is sorted (Ali and Ethan know what they're designing)
- Elevators, vacuum systems, sensors, cameras (3 cameras?)
- Let Cindy + Orson know camera amounts
- Some dongle to combine camera feeds into one?
- Encoders still a W.I.P
- Probably having Pololu motors everywhere, and some servos
- Austin and Emily picked actuators
- All actuators have been purchased (Austin dealing with YEP program)
- Going back and forth with Gleeson
- Electrical
- Wolfgang and a new member Ivan on Science board
- Based on mechanism from Ethan
- Gimbal board, schematic should be done soon, then onto layout
- PDB pushed back another week
- BMS (battery management system), measure charge, temp, board can charge/discharge the battery: progress being made, schematic should be wrapped up asap for firmware team
- All the juice does not pass through this board
- Wiring diagram can be done later (December)
- Find things for new members to do
- Started with multiphase buck converter, step down to 24V
- 2/3 weeks to get schematic volts
- Two 24 to 48 converters working out of phase with one another, they keep switching (control frequency and phase, reduce current, maximize efficiency)
- Firmware
- Science
- Onboarding new members over reading week
- Planning and scheduling out the science plan, how we're going to get that done, reach out to professional geologists and members in the science faculty
- 8 new members
- Business
- Working on the WEEF and deans list proposals
- Software
- Looking to have drivetrain code done by the end of October so Melvin can start testing on campus. Month of November dedicated to arm up and running.
- Ali wants to do controls (according to Ethan, Ali's in Mech, but doing some software things)
- Add to the GANTT chart
|